06 Chapter Six

The Programme.

One document, four phases, fifty-two tasks. The Combined Work Programme is the spine that connects Shell's findings, ISO 45001's clauses and the Seagull integrated management system into a single line of sight — from 5 February through to 3 May.

The Combined Work Programme — SM/INT/CMP/002replaces the two finding-by-finding Change Management Plans originally sent back to Shell on 6 February. Those plans would have closed the findings. They would not have done much more than that. When the Seagull Management Review sat down in February and looked honestly at the state of the wider system, the conclusion was clear: Shell's findings were not a problem to patch — they were a springboard. The CWP was built to capture that pivot. One single, colour-coded master. Every row ties to at least one of three anchors: an ISO 45001 clause, a Shell finding or OFI, or a deliverable in the wider management system rebuild. Nothing lives outside it. Nothing gets done twice.

The programme runs in four phases. Phase 1 (Foundation) and Phase 2 (Risk Framework & Core Procedures) are closed out. Phase 3 (Implementation & Evidence) is where we are now — training rollout on the LMS, internal audits in progress, management review done. Phase 4 (Certification & Review Ready) opens on 21 April with Libero's ISO 45001 Stage 2 on-site audit — Stage 1 (documentation review) is already done — and finishes on 3 May with Shell.

Live working document

Open the live Combined Work Programme

SM/INT/CMP/002 v2.0 — the full working spreadsheet. Six tabs: Dashboard, Master Programme, Shell Findings, Shell OFIs, 45001 Clauses, MS Transition. This is the file. Not a summary, not a screenshot.

Download CWP (.xlsx)
52
Tasks in the programme
4
Phases · Feb through May
35
Completed to date
25 / 25
ISO 45001 clauses covered
Section One · The four phases

Phased delivery, honest status

Every phase shown with live status against each task. Completed items carry their document reference. In-progress items are flagged honestly — we are not pretending Phase 4 has started. The only item outside our control sits in Phase 1 (Malta, Finding 1).

01
Phase One

Foundation — policies, legal, document control

February 2026
13 of 14 complete 1 external dependency (Malta)
1.01
Define OH&S management system scope
SM/HSE/DOC/001 · 45001 Cl. 4.3
Complete
1.02
Context of the Organisation — SWOT / PESTLE
SM/INT/DOC/002 · Pre-war v1.0 + Iran-escalation v2.0 · 45001 Cl. 4.1
Complete
1.03
Interested Parties Register (incl. VPSHR)
SM/HSE/REG/001 · 21 parties, Power/Interest matrix · F6 · 45001 Cl. 4.2
Complete
1.04
OH&S Policy — reissue with VPSHR & 45001 commitments
SM/HSE/POL/001 · F6 · 45001 Cl. 5.2
Complete
1.05
Legal & Regulatory Requirements Register
SM/HSE/REG/002 · 37 entries across 5 jurisdictions · F1 · 45001 Cl. 6.1.3
Complete
1.06
Management of Change Procedure + form + register
SM/INT/PRO/013 FORM/003 REG/009 · OFI1 · 45001 Cl. 8.1.3
Complete
1.07
Media & Social Media Policy — finalise and issue
SM/INT/POL/008 · F3 · 45001 Cl. 7.4
Complete
1.08
Drugs & Alcohol Policy — scope across all personnel
SM/INT/POL/010 SM/INT/PRO/021 · OFI7
Complete
1.09
Document Control Procedure — update for 45001
SM/INT/PRO/002 · 45001 Cl. 7.5
Complete
1.10
Sanctions screening — embed OFAC / US check
SM/INT/POL/002 · 30K-entry Sanctions Screener Tool · OFI3
Complete
1.11
Malta exemption letter — chase and document
F1 · Formal request lodged · Escalation issued 9 April 2026 · Malta Security Service response awaited
External
1.12
Insurance documentation alignment
F4 · Cover and certificates reissued
Complete
1.14
Internal Audit Programme review & gap analysis
SM/INT/RPT/001 · Self-review produced, NCRs raised · 45001 Cl. 9.2
Complete
1.15
Internal Audit Schedule 2026 — 12-month rolling
SM/INT/REG/003 · 45001 Cl. 9.2
Complete
02
Phase Two

Risk framework & core procedures

March 2026
15 of 17 complete 1 in progress · 1 pending (MOU training)
2.01
Hazard ID & Risk Assessment Procedure
SM/HSE/PRO/001 · F2 · 45001 Cl. 6.1.1 & 6.1.2
Complete
2.02
OH&S Objectives, Targets & KPIs
SM/INT/REG/006 · 32 SMART objectives · 45001 Cl. 6.2
Complete
2.03
Roles, Responsibilities & Authorities matrix
SM/INT/DOC/005 · 48 functions, 11 role categories · 45001 Cl. 5.3
Complete
2.04
Worker Consultation & Participation Procedure
SM/INT/PRO/014 · 10 sections · 45001 Cl. 5.4
Complete
2.05
Emergency Preparedness & Response Procedure
SM/HSE/PRO/003 · F7 · 45001 Cl. 8.2
Complete
2.06
Incident & Crisis Management Procedure
SM/INT/PRO/006 · 45001 Cl. 10.1
Complete
2.07
NCR / OFI / CAPA Procedure + Register + Form
SM/INT/PRO/001 REG/004 FORM/001 · 45001 Cl. 10.2
Complete
2.08
VPSHR integration — embed into operational documents
F6 · Embedded in IOR SOP, annexes, training decks, Code of Conduct — final sweep ongoing
In Progress
2.09
Procurement & Contractor H&S Procedure
SM/INT/PRO/017 · 45001 Cl. 8.1.4
Complete
2.10
SEV Minimum Standards — full supplier ecosystem
SM/SEC/PRO/004 PRO/005 FORM/001-004 · OFI6
Complete
2.11
Vessel delay wording — SOP amendment
IOR SOP Annex D · OFI4
Complete
2.12
UKMTO reporting — SOP amendment
IOR SOP Annex E · UKMTO as primary reporting channel · OFI5
Complete
2.13
Nigerian Navy MOU — training review
F5 · MOU received · Training component scope being defined with HR & Training
Pending
2.14
Management Review Procedure — update to 45001
SM/INT/PRO/019 · OFI2 · 45001 Cl. 9.3
Complete
2.15
Internal Audit Procedure — confirm 45001 alignment
SM/INT/PRO/003 · 45001 Cl. 9.2
Complete
2.17
9x H&S Risk Assessments created & distributed
SM/HSE/RA/002–010 · 144 hazards · F2 · 45001 Cl. 6.1.2
Complete
2.18
Continual Improvement Procedure
SM/INT/PRO/015 · 45001 Cl. 10.3
Complete
03
Phase Three

Implementation & evidence — training, audit, review

April 2026
7 of 11 complete 3 in progress · 2 pending (MS transition, MOU training)
3.01
Training needs analysis — all new & amended procedures
SM/INT/PRO/012 · 45001 Cl. 7.2
Complete
3.02
Training programme — design & schedule
21 courses built in PptxGenJS · LMS deployment configured · F2, F3, F6 · 45001 Cl. 7.2 & 7.3
Complete
3.03
Training rollout — Batch 1 (core H&S, MoC, incident)
LMS live 8 April · Courses deployed · Pavel-endorsed 20 April deadline · F2, OFI1
In Progress
3.04
Training rollout — Batch 2 (media, VPSHR, D&A)
All courses live on LMS · Completion tracked via "At Risk" tab · F3, F6, OFI7
In Progress
3.05
PCASP briefing to Masters — formalise and distribute
Masters Briefing v2.0 (15 slides) · Skiff ID Guide IOR + SRS-GoA · OFI8
Complete
3.06
IRT Exercise — plan, conduct, document
SM/HSE/RPT/001 · Piraeus office fire scenario · F7 · 45001 Cl. 8.2
Complete
3.07
Management Review #1 — conducted to 45001 agenda
SM-INT-MRM-001 v1.1 · Data maturity note included · OFI2 · 45001 Cl. 9.3
Complete
3.08
Internal Audit — 2 audits complete, more scheduled
IA-26-001 (Doc Control) + IA-26-002 (Risk Mgmt) with live CMPs · 45001 Cl. 9.2
In Progress
3.09
Competence assessment matrix — high-risk roles
SM/INT/REG/008 · 21 courses × 3 role categories × 41 personnel · 45001 Cl. 7.2
Complete
3.10
Legal register — responsible person review
SM/HSE/REG/002 · Review cycle embedded · 45001 Cl. 6.1.3 & 9.1.2
Complete
3.12
Nigerian Navy MOU training — delivered
F5 · Dependent on 2.13 scope definition
Pending
04
Phase Four

Certification & review ready

April – May 2026
1 of 8 complete Libero Stage 2 on-site 21 April · Shell close-out 3 May
4.00
ISO 45001 Stage 1 Audit — Documentation Review
Libero · Documentation pack submitted · Group certification scope with entity annex accepted
Complete
4.01
ISO 45001 Stage 2 Audit — On-Site
Libero · 21–25 April 2026 · Flights booked · Live system walk-through against all 25 clauses
Scheduled
4.02
Stage 2 nonconformities — address any findings
Buffer week before Shell · Corrective action records via NCR / CAPA register
Scheduled
4.03
Shell review preparation — compile evidence pack
F1–F7 · Week of 28 April · Chapter 05 of this portal IS the pack
Scheduled
4.04
Shell close-out — 3 May 2026 (provisional)
Andy Keane / Dennis Kerlin / Neil Murray · Likely remote format
Scheduled
4.05
Post-Shell review actions (if any)
Action tracker · Captured via NCR/OFI/CAPA register
Pending
4.06
ISO 45001 certification issuance & surveillance planning
Post-Stage 2 · Certificate issued by Libero · Year 1 surveillance cycle scoped
Pending
4.07
Continual improvement cycle — documented
Improvement log entries · 45001 Cl. 10.3 · Ongoing from 1 May
Ongoing
Section Two · ISO 45001 coverage

Every clause, evidenced

The CWP carries a live dashboard tab cross-referencing every ISO 45001:2018 clause to the Seagull document or evidence that demonstrates conformance. All 25 clauses are currently green. The Shell findings thread through it as overlaps, not as a separate workstream.

ISO 45001:2018 Clause Compliance Register

25 of 25 clauses covered · Complete
4.1
Context
4.2
Interested parties
4.3
Scope
4.4
OH&S MS
5.1
Leadership
5.2
OH&S Policy
5.3
Roles / RACI
5.4
Consultation
6.1.1
Risks & ops
6.1.2
Hazard ID
6.1.3
Legal reqs
6.1.4
Planning action
6.2
Objectives
7.1
Resources
7.2
Competence
7.3
Awareness
7.4
Communication
7.5
Documented info
8.1.1
Ops planning
8.1.2
Hazard elim.
8.1.3
MoC
8.1.4
Procurement
8.2
Emergency
9.1
Monitoring
9.2
Internal audit
9.3
Mgmt review
10.1
Incident / NC
10.2
Corrective action
10.3
Continual improve
The road to 3 May

What's left on the programme between now and the close-out visit

Two workstreams stay live until Shell reconnect with us. Training completion on the LMS — Pavel's hard deadline of 20 April, with completion rates tracked on the "At Risk" tab. And Libero's Stage 2 on-site audit, opening on 21 April with flights booked (Stage 1 documentation review is already behind us). The buffer week between Stage 2 and Shell exists on purpose: any Stage 2 nonconformity is already scoped into the CAPA process, and the Chapter 05 evidence pack is ready to be lifted straight off this portal on the day.